Computer Science 2023 Question 3. Critical Chain Scheduling
2023 I NEED IN THE NEXT 2 HOURS SEE ATACHED FOR CLARITY Project Time Management Exercise Do not use any | Assignment Collections
I NEED IN THE NEXT 2 HOURS:
SEE ATACHED FOR CLARITY
Project Time Management Exercise
Do not use any MS-Project for this homework
Question 3. Critical Chain Scheduling
Consider the following network diagram information
Task |
Predecessor |
Duration (weeks) |
A |
|
3 |
B |
A |
5 (4) |
C |
A |
4 (3) |
D |
B |
1 |
E |
C, D |
2 |
(a) Draw any network diagram which shows the precedence relationship and Identify the critical path and the length of it.
(b) Suppose that the task B and task C are performed by the same resource (only one unit), and it has been decided that the task B is going to be conducted earlier than the task C – this creates a new precedence relationship between B and C due to the resource. The new duration by the single unit is 4 and 3 for B and C, respectively. Now identify the critical path again here – This new critical path may be called a critical chain if we assume that this reduced task duration is very aggressive compared to previous task durations.
(c) Consider the new critical path obtained in part (b) as a critical chain. Then, draw a network diagram to show the critical chain with project buffer(s) and feeding buffer(s) – you do not need to describe the duration of buffers.
SEE TH
We give our students 100% satisfaction with their assignments, which is one of the most important reasons students prefer us to other helpers. Our professional group and planners have more than ten years of rich experience. The only reason is that we have successfully helped more than 100000 students with their assignments on our inception days. Our expert group has more than 2200 professionals in different topics, and that is not all; we get more than 300 jobs every day more than 90% of the assignment get the conversion for payment.