Read and analyze the Greendale Stadium case presented on pages 202-203 of Project Management: The Managerial Process.
Construct a network schedule (Gantt chart) in Microsoft® Project 2013 for the stadium project, using the information provided in the case.
Answer the following questions in a 1-page memorandum:
- Will the project be able to be completed by the May 20 deadline? How long will it take?
- What is the critical path for the project?
- Based on the schedule would you recommend that G&E pursue this contact? Why?
Submit the memorandum and the Microsoft® Project file showing the network schedule to the Assignment Files tab.
image
The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the construction of the upper steel bowl can occur (120 days).
Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes (90 days), installing the seats (140 days), installing the jumbotron (30 days), and installing stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lights (30 days).
The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower concrete bowl is constructed. At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed then the roof can be installed and made operational (90 days). Once all activities are completed it will take 20 days to inspect the stadium.
For purposes of this case assume the following:
The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.
The construction crew work Monday through Friday.
We give our students 100% satisfaction with their assignments, which is one of the most important reasons students prefer us to other helpers. Our professional group and planners have more than ten years of rich experience. The only reason is that we have successfully helped more than 100000 students with their assignments on our inception days. Our expert group has more than 2200 professionals in different topics, and that is not all; we get more than 300 jobs every day more than 90% of the assignment get the conversion for payment.