2023 Students must read the case study Teloxy Engineering A on page 948 and answer the corresponding | Assignment Collections
Computer Science 2023 Discussion
2023 Students must read the case study Teloxy Engineering A on page 948 and answer the corresponding | Assignment Collections
Students must read the case study “Teloxy Engineering (A)” on page 948 and answer the corresponding questions on the same page.
Discussions will consist of 2 parts: Your primary posting on the subject, and responses to two or more students postings. The primary post should be at least 300 words in length.
All initial postings must have reference from at least two peer reviewed academic journal articles or reference and it must be in APA format.
TELOXY ENGINEERING (A)
CASE STUDIES
Teloxy Engineering has received a one-time contract to design and build 10,000 units of a new product. During the proposal process, management felt that the new product could be designed and manufactured at a low cost. One of the ingredients necessary to build the product was a small component that could be purchased for $60 in the marketplace, including quantity dis- counts. Accordingly, management budgeted $650,000 for the purchasing and handling of 10,000 components plus scrap.
During the design stage, your engineering team informs you that the final design will require a somewhat higher-grade component that sells for $72 with quantity discounts. The new price is substantially higher than you had budgeted for. This will create a cost overrun.
You meet with your manufacturing team to see if they can manufacture the component at a cheaper price than buying it from the outside. Your manufacturing team informs you that they can produce a maximum of 10,000 units, just enough to fulfill your contract. The setup cost will be $100,000 and the raw material cost is $40 per component. Since Teloxy has never manu- factured this product before, manufacturing expects the following defects:
Percent defective 0 10 20 30 40 Probability of 10 20 30 25 15
occurrence
All defective parts must be removed and repaired at a cost of $120 per part.
1. Usingexpectedvalue,isiteconomicallybettertomakeorbuythecomponent? 2. Strategicallythinking,whymightmanagementoptforotherthanthemosteconomical
choice?
We give our students 100% satisfaction with their assignments, which is one of the most important reasons students prefer us to other helpers. Our professional group and planners have more than ten years of rich experience. The only reason is that we have successfully helped more than 100000 students with their assignments on our inception days. Our expert group has more than 2200 professionals in different topics, and that is not all; we get more than 300 jobs every day more than 90% of the assignment get the conversion for payment.