1. Using a project start time of 0 (or January 1) and a required project completion time of 180 days (or June 30), calculate the ES, EF, LS, and LF times and total slack for each activity. If your calculations result in a project schedule with negative total slack, revise the project scope, activity estimated durations, and/or sequence or dependent relationships among activities to arrive at an acceptable baseline schedule for completing the project within 180 days (or by June 30). Describe the revisions you made.
Responses could be presented in a network diagram or in the schedule table format. The project should finish in 180 days. If the original plan is not completed by 180 days, the responses should describe what tasks were revised to meet the required completion date.
2. Determine the critical path and identify the activities that make up the critical path.
Responses can be presented in a list of activity names, highlighted in the network diagram, or highlighted in the schedule table.
We give our students 100% satisfaction with their assignments, which is one of the most important reasons students prefer us to other helpers. Our professional group and planners have more than ten years of rich experience. The only reason is that we have successfully helped more than 100000 students with their assignments on our inception days. Our expert group has more than 2200 professionals in different topics, and that is not all; we get more than 300 jobs every day more than 90% of the assignment get the conversion for payment.